Commissioning brief: ABB AF80-30-00-11,1SBL397001R1100
Use the complete ABB AF80-30-00-11,1SBL397001R1100 designation for the purchase and asset record. The short family mark alone cannot establish electrical ratings, process options or interchangeability.
Technical selection record
| Technical item | Verified value / selection note |
|---|---|
| Complete designation | AF80-30-00-11,1SBL397001R1100 |
| Product family | AF80 |
| Component role | three-pole AF80 motor contactor |
| Frame | AF80 |
| Main contacts | 3 normally-open |
| Control coil | 24-60 V AC or 20-60 V DC |
| Auxiliary contacts | No built-in auxiliary in -00 variant |
| Order code | 1SBL397001R1100 |
| Final configuration | Confirm exact nameplate, hardware revision and order options before purchase |
Values shown for AF80-30-00-11,1SBL397001R1100 are selection checkpoints. Confirm the fitted unit, nameplate and ABB documentation before releasing an order or a site change.
Application decision
The intended duty of AF80-30-00-11,1SBL397001R1100 is to switch the assigned higher-current three-phase motor circuit. Record the controlled asset, panel location and circuit or process tag next to the exact code.
A specification for AF80-30-00-11,1SBL397001R1100 should state the operating conditions rather than assuming another AF80 item is a drop-in replacement.
Fit and interface gate
Compare AF80-30-00-11,1SBL397001R1100 with the existing installation for motor full-load current, switching category, coil, overload relay, cable bars and mechanical space. Keep photos of the nameplate, terminals and accessory arrangement with the enquiry.
If any connector, protective rating or configuration item differs, hold the AF80-30-00-11,1SBL397001R1100 substitution for engineering review.
Installation sequence
Before fitting AF80-30-00-11,1SBL397001R1100, isolate the affected system by the plant procedure and preserve the approved settings or wiring schedule. Verify mechanical seating and each identified connection.
After connecting AF80-30-00-11,1SBL397001R1100, check power, communications and local indications before enabling the controlled equipment.
Acceptance evidence
At handover for AF80-30-00-11,1SBL397001R1100, prove pickup, drop-out, three-pole continuity and overload feedback. Record who witnessed the test, the measured results and any open action.
The AF80-30-00-11,1SBL397001R1100 asset record should retain the final configuration, revision and commissioning evidence for later troubleshooting.
Related configuration codes
Other AF80 designations recorded with AF80-30-00-11,1SBL397001R1100 are shown below for search and enquiry. Their options and ratings can differ; the list does not claim automatic interchangeability.
- AF80-30-00-13
Purchase handoff
Quote the complete AF80-30-00-11,1SBL397001R1100 designation, the installation tag and the critical interface checks. Ask for nameplate and revision confirmation before dispatch.
When AF80-30-00-11,1SBL397001R1100 arrives, compare the received unit to the approved selection record and document the final acceptance result.